PONCHATOULA—Striping work is expected to begin on the recently paved portion of Sisters Road this week.
Tangipahoa Parish President Robby Miller said the RPC contractor will be striping Sisters Road over the next few days. It’s the latest in a series of projects being tackled on heavily-traveled roadways in southern Tangipahoa Parish.
Also on the calendar this week are several Phase 22 parish wide projects, including:
Soil Cement: Wilson Road, LA Polo Farm, Spirit of the Forest, Song of the Forest, Riverdale Heights, Brignac Road, Company Road, Thurland McGee Road;
Dressing: Mayeaux, Crapanzano, Cannino Road, East Merry, Nicholas, Blaire Boulevard, Milan, Naples Boulevard, Kayla, Penny, North and East Charbonnet Road, Bella Gardens, Blythwood, Wood Avenue, Crown Drive;
Paving: Blythwood Boulevard, Bella Gardens Circle, Audubon Drive, Ott Lane, Sewer Treatment Plant Road; and
Patching: Audubon Road, Sewer Treatment Plant Road, Bradford, Wilson, and LA Polo Farms Road.
All work is weather-permitting. Any related closures will be posted on the day of construction.