While road crews will work an abbreviated week due to the Memorial Day holiday, Tangipahoa Parish President Robby Miller says Barriere Construction has scheduled an ambitious list of tasks for the week of May 27.
Crews took Monday off in observance of the Memorial Day holiday; however, road work will kick off again in earnest on Tuesday with a heavy schedule of projects planned during the remainder of the week, including:
- Soil cement operations are scheduled on Chemeketee, Gemstone, Frank Lane, and Jaelyn Drive;
- Preliminary asphalt patching is planned for Trabona, North Peckerwood, West Martin Luther King, Mandella, Whitman, North Duncan, and South Lewiston;
- Asphalt paving will begin on Calvary, North Billville, East Park, Briarwood, Arboreal, Oak Hollow, and Holly;
- Milling operations are scheduled on West Black Cat, New Gennessee, South Lewiston, Woodstone, West Martin Luther King, and Mandella;
- Shoulder dressing continues on Old Covington, South I-12 Service Road, North Billville, Calvary, and Lark;
- Permanent striping operations are planned on Chappapeela, South I-12 Service Road, Old Covington, Brown Road, Happywoods, Whiskey Lane, and Wadesboro.
All work is weather permitting, and intermittent delays should be expected. Motorists are encouraged to take alternate routes, if at all possible.
For more updates on road work in Tangipahoa Parish, consult the Tangipahoa.org website and the TPG social media channels.