AMITE—The official start of summer is just a few days away, and that means the Phase 2023 overlay program is moving full-speed ahead, Tangipahoa Parish President Robby Miller said.
“Our crews are making good use of the longer days to get the Phase 2023 road program off to a positive start,” Miller said.
During the week of June 19, crews will be working in the following areas:
- Paving: Mandela, Pine, Wilson Street, East 8th Street, East Alessi Road, Catfish Farm, Straughan Nursery, Thomas, Nuccio Road, McGee, Pisciotta, McManus, J.E. Joiner;
- Milling/Patching: Pinecrest Drive, M.C. Moore Road, Northwood Crossing, Oak Meadows Boulevard, Martino Lane, College Drive, Iverstine, West Lee Hughes, Wellington Lane, Cherie Drive, Iever Street, Burton Street;
- Dressing: Stateline Road;
- Patching: Chappapeela Road, Pinecrest Drive, M.C. Moore Road, College Drive, Northwood Crossing, Oak Meadows Boulevard, Martino Lane, Cherie Drive, Iever Street, and Burton;
- Cutting Cement: Recile and Graceland Road.
All work is weather-permitting. Miller asks motorists to continue to use caution in work zones.