KENTWOOD—Tangipahoa Parish will kick off 2023 with a busy week of overlay work across the parish.
Tangipahoa Parish President Robby Miller said the Phase 22 overlay project is scheduled to resume on Tuesday as crews plan to complete several paving and shoulder dressing projects.
During the week of January 3-6, soil cement work is planned on Premo Road in Tickfaw.
Crews are scheduled to pave Willie McCoy Road, East Mulberry Street, Wallace Court, Company Road, Verberne Road, Rhodus Road, Thurland McGehee Road, Joe Dyson Road, and Hunt Road.
Dressing work is planned on Bradford Road, Wilson Road, LA Polo Farms Road, Song of the Forest Road, Spirit of the Forest Road, North Riverdale Heights Road, Brignac Road, and Company Road.
All work is weather-permitting. Any related closures will be posted on the day of construction.
Miller said RPC crews will continue to replace mailboxes on Rufus Bankston Road, Wardline Road, and North Baptist Road during this week.