FOR IMMEDIATE RELEASE
Contact: Tangipahoa Parish President Robby Miller
(985) 748-3211
AMITE—Despite limited rain delays late last week, the contractor expects to push forward on several overlay projects this coming week.
Tangipahoa Parish President Robby Miller said the weather has been fairly cooperative in these early stages of the Phase 22 overlay project.
“We are pleased with the progress so far,” Miller said, noting that road work is ongoing in all 10 Parish Council districts.
Next week’s schedule includes work in the following areas:
*Monday, June 13: Paving on Rohner Road; milling and patching on Lee Farm Road and Wadesboro Road; patching on South Elm, Fern Street, and Lee Farm Road; dressing on Fontana Road, Charles Sinagra, Pine Street, Black Cat, and Maggio Road crossings, and North Wilson Street;
*Tuesday, June 14: Paving on Morris Retreat and Dummyline; milling and patching on North Rateau and 11th Street and Rue Monet and Beckendorf; patching on South Elm, Fern Street, and Lee Farm Road; and dressing on Fontana Road, Charles Sinagra, Pine Street, Black Cat, and Maggio Road crossings, and North Wilson Street;
Wednesday, June 15: Paving on Morris Retreat and Dummyline; milling and patching on North Rateau and 11th Street and Mayeaux and Crapanzano Roads; patching on South Elm, Fern Street, and Lee Farm Road; and dressing on Tantillo/T Hardy and North Lee Hughes;
Thursday, June 16: Paving on West and East Bennett; milling and patching on Forest Lane and Celia Street; patching on South Elm, Fern Street, and Lee Farm Road; and dressing on West and East Green, North Wilson, and Western Avenue;
Friday, June 17: Paving on Natchez and Mooney; milling and overlay on Audubon Road; patching on South Elm, Fern Street, and Lee Farm Road; milling and patching on Cannino Road; and dressing on Rohner, Dummyline, and Morris Retreat;
Saturday, June 18: Paving on South Elm Street and Fern Street; patching and overlay on Audubon Road; patching on South Elm, Fern Street, and Lee Farm Road; milling and patching on Cannino Road; and dressing on Rohner, Dummyline, and Morris Retreat.
In addition to these local road projects, Miller said the parish has received notice from DOTD of the following state project that is scheduled during the week of June 13:
*June 13-16: DOTD will be making cable barrier repairs on I-55 north and south of Amite. The roadway will not be closed; however, motorists can expect a partial lane closure in the left lane. Areas impacted include a portion of I-55 approximately 2.4 miles north of the Amite exit and a second portion located approximately eight-tenths of a mile south of the Amite exit.
Miller also reminded motorists that movie crews will be working in Tangipahoa Parish over the next few days. As a result, several local roads will be closed during filming, including:
*June 14-16: Wadesboro Road between Jones Road and Everett Lane. Traffic in that area will be closed to traffic between the hours of 6 a.m., and 10 p.m., each day;
*June 17: West Robinson Street, West Church Street, and West Dakota between Railroad Avenue and Oak Streets in Hammond will be closed to traffic. Additionally, there may be intermittent traffic delays in the area around NW Railroad Avenue and North Oak between Church Street and Carter Lane. Those closures are expected between the hours of 1-5 p.m.
For updates on local road conditions and road closure notices, consult the Tangipahoa Parish Government website (www.Tangipahoa.org) and the TPG social media channels.